From enquiry to bulk: the real timeline of a fabric order

Most delays are not production problems. They are approvals that sat in an inbox, or a mill schedule that was never checked before the ship date was promised.

By Weft Bridge · Reviewed by our Guangzhou sourcing team · Updated 2026-11

The stages

StageTypical durationWho is on the critical path
Quote and mill selection2–5 daysSupplier
Lab dip5–10 daysMill, then buyer approval
Sample yardage1–2 weeksMill
PO, deposit, yarn booking3–7 daysBuyer and mill
Weaving / knitting2–4 weeksMill
Dyeing and finishing1–2 weeksMill
Inspection1–3 daysInspector
Shipping booking3–7 daysForwarder

Where it actually slips

Two steps cause most of the delay: lab dip approval and the mill schedule. The first is usually the buyer — a dip sits unapproved for a week while the team debates a shade. The second is usually invisible until it is too late: the mill booked the dye line before the PO arrived.

Ask for the dye slot date before you confirm the ship date. If the mill cannot give a slot, the delivery date is a hope, not a plan.

A realistic buffer

  • Add one week for a first order with a new mill.
  • Add two weeks if the shade is difficult or the finishing is unusual.
  • Add the Chinese New Year shutdown if your window overlaps it — factories close for two to four weeks.
  • Do not compress the inspection stage; that is where problems are caught cheaply.

FAQ

Can a fabric order be done in four weeks?

For a stock quality in a stock colour, sometimes. For a new shade on a new quality, rarely.

What is the biggest schedule risk?

A promised ship date that was never checked against the mill dye schedule.